Steps In Construction of Residential Building

Building construction begins after the completion of documentation process.Some major steps in Construction of Residential Building are below -:

EARTH WORK

Generally excavation is carried out for the construction of wall foundations. Excavation should be carried out as per the drawings defined lengths & widths. After excavation, layout the foundation and backfill the remaining excavated area around foundation with soil.

Floor levels of residential buildings are higher than the natural ground level. Fill the area with soil up to floor levels and compact the soil. Now earth work of residential building is finished.

CONCRETE WORK IN FOUNDATION

It is very necessary to check the levels of foundation before concrete work. There are patches where excavated depth slightly exceeds and vice versa. Level the foundation base to same level. Now pour the concrete as per drawing specs. Generally concrete of ratio 1:4:8 is used for foundation. Sometimes it is even 1:5:10 or 1:6:20.

Here 1:4:8 means;

1 part cement per cubic

4 parts of sand per cubic

8 parts of coarse aggregates

Depth of foundation varies from 9” to 18” and normally for most of the cases it is considered as 12’’ depth. Keep foundation width equals to its depth.

DAMP PROOF COARSE (D.P.C)

To protect walls from moisture, a layer of damp proof coarse material is laid down at floor level. Thickness of this concrete layer is 0f 1 inch. Material of damp proof coarse layer consists of concrete ratio 1:1.5:3 with a mixture of water proof material 1kg/bag.

MASONRY WORK

Masonry work is carried out with cement mortar. Cement mortar is a mixture of cement & sand. Ratio of cement mortar varies from 1:4 to 1:6. Here (1:6) mean, 1 part cement and 6 parts of sand. Dampen about 25 bricks with a hose pipe and clean away all loose dirt from the top of footing and moisten about a meter of surface at one end of the foundation with the hose pipe. Throw a mortar line just behind the threaded level line and lay bricks on the mortar bed. Make sure bricks exactly follow the threaded horizontal level line.

LINTEL

Masonry work of buildings is carried out in one go till roof. Openings for windows & doors are left during masonry works. Reinforced cement concrete beams are laid down on the top of openings. So, those loads of structure above openings not directly come on to the door frames.

ROOFING

Roof slab of building is poured after completion of masonry works. Now a days, roofing is of reinforced cement concrete slab. Slab thickness & reinforcement details should be according to approved drawings.

PLASTERING & POINTING

Form work is removed after 14 days of slab pouring. Now plaster work begins. Mortar for plaster work is generally of 1:3 or 1:4 is used. Thickness of plaster layer should not be more than 0.75inch. Cure the surface about 7 days. So that, plaster gain proper strength.

Generally, internal walls of buildings are covered with plastered layer and external walls with pointing. It is better plaster the external walls rather than pointing.

DOORS & WINDOWS

Traditionally, doors and windows of woods are used. But, steel & aluminum is also not a bad choice. In case of wooden doors & windows, frames are fixed in walls during masonry work. Panels are then fixed with hinges after plaster work. Steel and aluminum doors are fixed after completion of paint work.

SERVICES

Services are very important for every single house. Different types of services are provided during construction. These are Electricity supply, gas supply, water supply, sanitary etc. Conduits for electric supply are fixed in walls before plastering. Similarly water supply and sanitary lines are also laid before pouring of building floor. Note that gas lines are not fixed in walls or slabs. Gas line remains open in air.